ERDC/CHL CHETN-II-47
March 2004
Figure 3. Post-fill March 1995 and 2 years later April 1997 at Sea Gate hot spot
being monitored. The project is divided into two sections with Section I extending from Sea Bright
to Ocean Township (Loch Arbour) and Section II extending from Asbury Park to Manasquan.
Section I has four reaches, one of which has not been constructed yet and Section II has two reaches
(Table 3). Figure 4 shows the complex sequence of construction and the location of the project's
three hot spots: (a) at Monmouth Beach, (b) at Spring Lake, and (c) the south end of the Sandy Hook
spit at Sea Bright.
Table 3
Construction Data for Sea Bright to Manasquan Inlet Beach Nourishment Project
Fill Qty
Contract
Contract Award
Beach Fill Complete
cu m
cu yd
Section I: Sea Bright to Ocean Township
1A (Monmouth)
January 1994
December 1995
3.5 million
4.6 million
1B (Sea Bright)
July 1995
November 1996
2.9 million
3.8 million
2 (Long Branch)
May 1997
December 1998
3.3 million
4.3 million
3 (Deal)
TBD
November 2003 (est)
3.8 million
5.0 million (est)
Section II: Asbury Park to Manasquan
1 (South Reach)
June 1997
October 1997
3.1 million
4.1 million
2 (North Reach)
June 1999
June 2000
2.4 million
3.1 million
Renourishment
August 2001
November 2002
1.7 million
2.24 million
Hot spot 1 at Monmouth Beach was located at the southern boundary of the first contract reach and
covered a 793-m (2,600-ft) section of contract area. The initial fill was placed in November 1994
with 396,827 cu m (519,000 cu yd) placed. To mitigate for the erosion experienced at this hot spot, a
second placement occurred in November 1995 with 175,858 cu m (230,000 cu yd) placed. A third
placement was needed in May 1998 with 431,234 cu m (564,000 cu yd) of fill placed. Through
monitoring and analysis it was determined that the cause was seaward perturbation of the beach due
to encroachment of the upland structures onto the beach and the design requirement of a uniform
6