CETN IV-20
September 1999
(Figure 4). We will assume a 40-percent uncertainty; thus QL-S = 100,000 40,000 m3/year.
These values are then entered into the sediment budget.
Figure 4. Macrobudget option within SBAS
Because right-directed transport has been assumed to be constant for the entire barrier, set values
of right-directed transport at the pre-inlet boundaries, Q4 and Q6 = 200,000 m3/year. Assume for
the pre-inlet condition that Q9=Q10=Q11=Q12=0. Use the residual values or the "force
balance cell" option for each cell to determine the unknowns. The final pre-inlet sediment
budget is shown in Figure 5.